Tentative schedule released for completion of Utility/Street Project

Weather permitting, work will be done by August 1

street
THE SUBCONTRACTOR FOR work done on the 2012-2014 Mountain Lake Utility/Street Project – French Lake – was busy doing concrete removal and replacement repairs along 2nd Avenue on Thursday afternoon, July 10.

The City of Mountain Lake released a tentative schedule for completion of the work for the 2012-2014 Utility and Street Project area on Wednesday, July 9.

That scheduled is as follows:

This Week (Week of July 7)

* Hopeful that subcontractor (French Lake) will complete the concrete removal and replacement repairs.

* Televising subcontractor is scheduled to be on site on Thursday, July 10 and thereafter to complete the sanitary sewer televising.

* Mud jacking subcontractor was on site today (Wednesday, July 9) and anticipates being on site about a week completing the mud jacking/void filling work.

* Kuechle Underground, Inc. crew working on punch list items.

Week of July 14

* Finish the mud jacking work.

* Leveling of boulevards and turf restoration.

* Kuechle crew working on punch list items.

Week of July 21

* Leveling of boulevards and turf restoration.

* Subcontractor (Legends Concrete) scheduled to be on site to complete the last of the concrete walk construction and any remaining corrective replacements.

* Subcontractor (SMC – Southern Minnesota Construction) tentatively scheduled to be on site to do the leveling of the non-wearing course pavement.  Leveling work will probably include a combination of pavement removal, gravel leveling and repaving along with overlay work.

* Kuechle crew working on punch list items.

Week of July 28

* Subcontractor (SMC) on site paving the bituminous wearing course.

* Kuechle crew working on punch list items.

Friday, August 1

* Weather permitting, work is completed.

The above tentative schedule is dependent upon favorable weather in Mountain Lake and at the other sites where the subcontractors are currently working.  The tentative schedule will be accelerated whenever possible based on windows of opportunity that arise for the subcontractors to be on site to complete the work.

Questions and concerns should be directed to City Hall 427-2999.

 